Newsletter Signup
The Austin Monitor thanks its sponsors. Become one.
Most Popular Stories
- Austin unveils how light-rail could change the city in new report with detailed maps
- Dirty no more? City opts to keep Sixth Street open to traffic at all times
- Lost Creek neighborhood sues city over tax efforts
- Density proponents encouraged by HOME six-month progress report
- Most Austin-area drivers will still need a vehicle inspection. Here’s where the rules have changed.
-
Discover News By District
Popular Whispers
- DAA lunch talk looks at future of I-35 amid expansion, cap-and-stitch concerns
- City is preserving affordable housing near the Domain
- SBA issues grant to open office for women entrepreneurs in Austin
- Report: Austin home prices grew 85 percent since 2014
- Share your thoughts on CapMetro’s proposed upgrades for payment options
Plans moving forward to construct Waller Creek tunnel
Monday, April 19, 2010 by John Davidson
The Waller Creek Master Plan, unveiled at a town hall meeting April 7 to spirited discussion of how to pay for it, aims to create a luxurious pedestrian- and bike-friendly greenbelt stretching from Waterloo Park to Lady Bird Lake.
And although models and maps of what the master plan might someday produce are striking, they are perhaps not quite as striking as the very real plans for the Waller Creek tunnel, a massive subterranean flood diversion channel upon which the future of the Waller Creek District rests.
In fact, plans for a river walk and any other development in the Waller Creek District depend on the tunnel, according to City of
“Much of it has been either inundated by flood and debris or actually destroyed in some locations,” he said. “If you go along the creek you’ll see serious bank erosion. Some buildings and utilities are exposed and overhanging the creek. The foundations have been undermined by the erosion.”
The day before the town hall meeting,
Unlike the Waller Creek Master Plan, the tunnel has funding. A tax-increment financing district will pay for what
According to
The tunnel, which will be 70 feet underground, will only be visible above ground in a few places: the shaft between 4th and 5th streets, the inlet at
Although the tunnel project is still in the design phase, it’s actually made of about a dozen different projects, says
The building currently sits on what was determined to be the ideal location for the tunnel outlet, so the city is planning to demolish the building and build a new boat facility a little to the west. There has been considerable discussion about that but no final decision about what organizations or company will use that building. (See In Fact Daily, Sept. 17, 2009.) A handful of smaller projects related to preparation for tunnel construction are slated to begin construction this summer, according to