Photo by Michael Minasi/ KUT News. Construction workers were putting the final touches McKalla Station at Q2 Stadium ahead of Saturday's opening.

New Cap Metro train station opens at Q2 Stadium as ‘quiet zones’ take effect

Monday, February 26, 2024 by Nathan Bernier, KUT

Editors note: Since this story published, Capital Metro’s operations chief, Andy Skabowski, said he was mistaken about when quiet zones would take effect. In an interview with KUT, Skabowski apologized for his statements and clarified the quiet zone would start in six to eight weeks.

Q2 Stadium home of the Major League Soccer club Austin FC got a new Capital Metro train station this weekend. The $60 million McKalla Station, funded partly by the voter-approved Project Connect transit expansion, is designed to handle waves of soccer fans pouring out of the approximately 20,500-capacity sports facility.

“It’s supporting a big venue, but it also has a lasting connectivity, even when events are not around,” Capital Metro vice president Dave Kubicek said last week during media tours of the facility with transit agency executives. Kubicek oversaw the design and construction of the new Red Line station.

As the Cap Metro Rail (formerly MetroRail) station opened Saturday morning, people in North Austin finally got some auditory relief from all-day train horns. Long-awaited “quiet zones” took effect at Kramer Lane, Rutland Drive, Braker Lane and Rundberg Lane.

Those four crossings have been upgraded to meet more rigorous federal safety standards. Now, trains won’t be required to blast ear-piercing warning sounds that can be heard inside buildings blocks away.

CapMetro’s red line train passes through McKalla Station on Feb. 20, 2024, outside of Q2 Stadium.

Michael Minasi/KUT News. Capital Metro’s Red Line trains, which pass by more than 30 times a day, have had to blow their horns at four street crossings in North Austin. Quiet zones taking effect Saturday mean the ear-piercing horns won’t be required most of the time.

Capital Metro was rushing to get McKalla Station up and running in time for Austin FC’s first home match of the season on Saturday, a target set months ago after previous delays. Earlier last week, workers were still installing underground utilities and laying pavement for a 350-foot-long bus stop on Delta Drive right next to the station on the east side of Q2.

But landscaping hasn’t been completed. A mural by Austin artist J Muzacz still needs to be installed. Those finishing touches are slated to be done by April or May.

Additionally, a park-and-ride planned for Q2 Stadium’s East Lot has not been set up. Parking spaces will be available for free to people taking the train on days when no events are happening at the stadium.

“We’re moving as quickly as we can on that,” Kubicek vowed, but he couldn’t offer an estimate on when the park-and-ride would be available to train commuters.

McKalla Station has two sets of train tracks. The second set of rails allows Capital Metro to have trains ready to go in both directions after events at Q2. The first fans out of the stadium will be able to board a southbound train or northbound train immediately. Capital Metro’s rail yard is about a mile away, which allows for more trains to be sent quickly.

An aerial view of McKalla Station showing two sets of train tracks. Each platform has two canopies on each side for people to catch shade or avoid rain. Some parts of the station that will be landscaped are now just dirt and gravel.

Nathan Bernier/KUT News. McKalla Station has two sets of train tracks. Capital Metro can have trains waiting for passengers on one track while normal Red Line service continues on the other track.

“We’re probably looking at a 30 percent to 40 percent increase in train capacity after a game than what we had previous,” said Andy Skabowski, the Capital Metro vice president overseeing operations. “It means you’re going to get home a little faster.”

On Q2 event days, travelers heading to Leander Station will have the option of boarding a bus that goes straight to that northernmost stop on the 32-mile Red Line. Capital Metro will also run an express bus to Downtown Station, the southernmost stop.

“It gives them an opportunity to get home a little quicker and gives us a little more capacity on the train side,” Skabowski said.

Bus stops for the 803, 383 and 3 routes will stay where they are.

A map showing the various bus and train stations around Q2 Stadium.

Map by Capital Metro. Capital Metro says existing bus stops will stay where they are around Q2 Stadium. Express buses will take people directly to Red Line stations in Leander and downtown Austin after major events. The express buses will depart from Delta Drive, next to McKalla Station.

Austin Stadco, the company behind Q2 Stadium, is kicking in $3,650,000 for McKalla Station under an agreement with Capital Metro. Most of that will be paid in installments over 15 years. A big chunk of cash for McKalla – $25 million – comes from the Project Connect property tax increase approved by voters in 2020. The rest of the $60 million comes out of Capital Metro’s budget, which is mostly funded by a 1 percent sales tax.

Capital Metro’s agreement with Austin Stadco included the possibility of a pedestrian tunnel under the tracks or a bridge over them. That plan was abandoned. People will have to walk directly over the train tracks. Safety gates block the pedestrian crossing when a train is coming.

The transit agency also gets exclusive use of Q2 Stadium for one day per year without having to pay venue rental fees. Capital Metro executives at the media tour last week weren’t aware of any such events planned at Q2 for 2024.

McKalla Station was supposed to replace Kramer Station, which is less than half a mile away. But Capital Metro hasn’t set a date to close Kramer because of delays in completing another Red Line stop near the Domain.

Broadmoor Station which is slated to have two double-length, covered platforms had been scheduled to open this year. But construction hasn’t even started on the station at a 66-acre mixed-use development called Uptown ATX.

A rendering showing Broadmoor station with two sets of train tracks and canopies for passengers on both sides.

Image by Capital Metro. A rendering showing Broadmoor Station planned to be constructed at Uptown ATX near the Domain. The station was supposed to be done this year. Right now, there’s no timeline for when it will be done.

Capital Metro has offered some explanations for the Broadmoor delay, blaming mostly “Covid-related market impacts” on the Uptown ATX development and challenges getting city permits.

“We do not have a timeline to share today,” said Sharmila Mukherjee, a Capital Metro vice president in charge of planning. “We are progressing well in the discussion, but for a while there was no discussion because we were essentially waiting to get all of the arrangements and agreements sorted out.”

Broadmoor Station is a public-private partnership, so the estimated $24 million price tag was planned to be split evenly between Capital Metro and Uptown ATX developer Brandywine Realty Trust.

A year-old filing with the state, first reported by the Austin American-Statesman, suggested Broadmoor Station could be completed by June 2025. The cost of the Red Line station, according to the filing, had grown by almost 50 percent to more than $35 million.

This story was produced as part of the Austin Monitor’s reporting partnership with KUT.

The Austin Monitor’s work is made possible by donations from the community. Though our reporting covers donors from time to time, we are careful to keep business and editorial efforts separate while maintaining transparency. A complete list of donors is available here, and our code of ethics is explained here.

You're a community leader

And we’re honored you look to us for serious, in-depth news. You know a strong community needs local and dedicated watchdog reporting. We’re here for you and that won’t change. Now will you take the powerful next step and support our nonprofit news organization?

Back to Top